District cooling ETS rooms: getting to first-time approval
The energy transfer station is where the building meets the network. Most rejected inspections come down to four things.
MEP contractor, with civil engineering under the same roof. Dubai, since 2004.

Approved contractors carry the submissions, inspections and energisation of 11 kV and LV works. Here is where that saves time, and where it does not.
Every new building in Dubai connects to the DEWA network through an approved contractor. For low and medium voltage works that means a contractor on DEWA’s approved list, responsible for the submissions, the inspections and the energisation of the installation. AZEMCO is one of 13 such contractors in Dubai.
The time savings come early. An approved contractor knows the drawings, load schedules and test records DEWA expects, so submissions are right the first time. Inspection slots are booked against a programme that already allows for them, and test results arrive in the format the inspector needs.
Approval does not move a substation. If the plot needs a new 11 kV substation, the room, the ventilation, the access and the cable routes have to be agreed with the architect and the main contractor long before electrical works start. The most common delays we see are rooms that are too small and cable routes blocked by other services.
The energy transfer station is where the building meets the network. Most rejected inspections come down to four things.
Carports turn parking into generation. What we have learned building and maintaining plants for DEWA.
Trenches, sleeves, plinths and builder’s work sit between two trades. Putting both under one contract removes the gap.



Send the drawings, the BOQ or just the brief. Our estimation team replies within two working days.