Mina Rashid Marina, Phases 2 and 3
Cabling and firefighting networks for DP World’s redevelopment of Mina Rashid, with the Phase 3 11 kV networks completed on programme in February 2019.
- Client
- DP World
- Main contractor
- Shafa Al Nahdah
- Consultant
- NEO Engineering Consultants
- Location
- Mina Rashid, Dubai
- Our role
- MEP subcontractor
- Contract value
- AED 20M
- Status
- Completed February 2019

New networks under a working estate.
DP World’s redevelopment of Mina Rashid turned Dubai’s historic port into a waterfront district with a marina. Working for the main contractor, Shafa Al Nahdah, AZEMCO installed the cabling and firefighting networks across Phases 2 and 3, including the 11 kV networks of Phase 3, while the estate around them stayed in use.
- 11 kV and LV cabling and a firefighting network across Phases 2 and 3
- Work that fitted around an estate in daily use
- The Phase 3 11 kV networks ready on the main contractor’s programme
What made it hard.
- 01
An estate in daily use
Trenching, cable pulling and pipe laying had to fit around traffic, operations and other contractors on an estate that never closed.
- 02
Two networks in the same corridors
The 11 kV cables and the firefighting mains often shared routes, so they had to be planned together to keep the separation and access each needs.
- 03
A fixed date for Phase 3
The Phase 3 11 kV networks had to be ready for energisation on the main contractor’s programme, with no room to slip.
What we did about each one.
- Challenge 01An estate in daily useOur response
Short sections, reinstated as we went
We opened the routes in short sections, with traffic management and permits, and reinstated each one before moving on, so the estate kept working around us.
- Challenge 02Two networks in the same corridorsOur response
One route plan for both networks
Our engineers set out the cable and hydrant routes together, with crossings, separations and valve chambers fixed before any excavation.
- Challenge 03A fixed date for Phase 3Our response
Daily coordination with the main contractor
We planned each week against Shafa Al Nahdah’s programme and coordinated daily with the other trades. The Phase 3 11 kV networks were completed on programme in February 2019.
From the first drawing to handover.
- 01Set-outRoutes for the cables and the hydrant mains surveyed and set out together.
- 02Trenching and ductsTrenches opened in short sections, ducts and pipes laid, and the ground reinstated.
- 03Cables and jointing11 kV and LV cables pulled, jointed and terminated.
- 04Firefighting networkHydrant mains, valves and hydrants installed and pressure tested.
- 05Testing and handoverCables tested before energisation, and the networks handed over on programme.
The Phase 3 11 kV networks were completed on programme in February 2019, and the main contractor wrote to thank the team.
- Phase 3 11 kV networks completed on programme in February 2019
- Firefighting networks in place across the working estate
- A letter of appreciation from the main contractor
During the course of the project the AZEMCO team have shown an immense degree of planning, co-ordination, safety and quality of workmanship. They have made this project a success by completing it in time.