Case study · District cooling

Empower semi-permanent chiller plants

HV and LV electrical works for Empower’s semi-permanent chiller plants, delivered plant after plant under repeat orders, inside a live district cooling network.

Delivered for
Client
Empower
Location
Dubai
Our role
HV and LV contractor
Contract value
AED 32M
Status
Completed
Approvals
Tests on Completion passed; taking-over certificate signed by Empower
Empower semi-permanent chiller plants
AED 32Mcontract value
2services in one contract
Handed overand in operation
The brief

Cooling capacity, connected while the network keeps running.

Empower uses semi-permanent chiller plants to meet demand while permanent capacity is built. Each plant needs its own HV and LV supply, connected and proven on a short programme, without disturbing the customers already on the network.

What the client needed
  • Each plant powered and running on a short programme
  • Connections made inside Empower’s live network, with its operations team
  • Every plant accepted against Empower’s own Tests on Completion
The challenges

What made it hard.

  1. 01

    Short programmes, plant after plant

    Each plant had to go from an empty plot to a running chiller plant quickly, and the next order often came before the last plant was closed.

  2. 02

    A live network

    New plants were connected to a network already cooling occupied buildings, so every shutdown and switching operation had to be agreed with Empower’s operations team.

  3. 03

    Acceptance on the client’s terms

    Empower takes over a plant only when it passes its own Tests on Completion, witnessed by its engineers.

How we solved them

What we did about each one.

  1. Challenge 01Short programmes, plant after plant
    Our response

    A method that repeats

    We set one way of working for every plant: the same cable routes and containment, switchgear connections, distribution and test sheets, so each new order started from a proven method and a trained crew.

  2. Challenge 02A live network
    Our response

    Switching planned with the operator

    Shutdowns and connections were planned with Empower’s operations team and carried out under permits to work, at times that kept customers cooled.

  3. Challenge 03Acceptance on the client’s terms
    Our response

    Tested before the witnesses arrived

    Our testing engineers ran the insulation, continuity, protection and function tests first, so the witnessed Tests on Completion confirmed results we already had.

How the work ran

From the first drawing to handover.

  1. 01SurveyEach plot surveyed and the supply route agreed with Empower.
  2. 02CablingHV and LV cables laid, glanded and terminated, with their containment.
  3. 03ConnectionSwitchgear, transformers and distribution boards connected to each plant.
  4. 04TestingInsulation, protection and function tests, then the witnessed Tests on Completion.
  5. 05Taking overEach plant handed to Empower’s operations team, and the next order begun.
The result

Every plant passed Empower’s Tests on Completion, and AZEMCO is Empower’s sole approved MEP contractor for MV, LV and HV works.

What changed
  • Plants connected under repeat orders rather than one-off tenders
  • Works accepted against Empower’s own Tests on Completion
  • Sole approved MEP contractor status for MV, LV and HV works