FedEx Sort and Clearance Facility
Design and build MEP for FedEx’s first sort and clearance facility in Dubai, with its own district cooling plant and energy transfer station, under one contract.
- Client
- Dubai South / FedEx
- Main contractor
- RAQ Contracting
- Consultant
- Plant Quadrant
- Location
- Dubai South
- Our role
- Design and build
- Contract value
- AED 60M
- Status
- Completed

A sort facility has to work from its first shift.
FedEx’s sort and clearance facility at Dubai South handles parcels on tight daily cycles. Dubai South and FedEx wanted one contractor to design and build every building service: power for the sort systems and the offices, cooling from a district cooling plant on the same plot, water and drainage, fire protection and the building controls.
- One party responsible for every building service, from design to handover
- A district cooling plant and energy transfer station on the plot, inside the same contract
- Every system tested together before the sort hall went live
What made it hard.
- 01
Everything ready at once
A sort hall cannot open in stages. Power, cooling, fire protection and controls had to be complete, tested and accepted together before the first shift.
- 02
A cooling plant inside a building contract
The district cooling plant and the ETS room sat in the same contract as the building services, so the plant, the chilled water network and the air side had to work as one system.
- 03
Design, approvals and site in parallel
As the design and build contractor, we carried the design. Drawings, authority approvals and orders for long-lead plant had to stay ahead of the structure, so the site never waited for us.
What we did about each one.
- Challenge 01Everything ready at onceOur response
Tested as one building
Our commissioning engineers tested each system on its own, then the links between them, such as the fire alarm’s signals to the air handling units and the controls’ view of every item of plant, before the building was handed over.
- Challenge 02A cooling plant inside a building contractOur response
One design for the plant and the building
We designed the cooling plant, the ETS room and the air side together, sized to the sort hall’s loads, and ordered the chillers, pumps and switchgear early to protect the programme.
- Challenge 03Design, approvals and site in parallelOur response
One model, one programme
Our engineers coordinated the five services in one model and took them through to shop drawings, so clashes were solved on screen; our planners tied every submission and delivery to the main contractor’s programme.
From the first drawing to handover.
- 01DesignConcept to shop drawings for five services and the cooling plant, coordinated in one model.
- 02ApprovalsSubmissions to the authorities for power, fire protection and the cooling plant.
- 03ProcurementChillers, pumps, switchgear and fire systems ordered early, against the programme.
- 04InstallationServices installed behind the structure; plant rooms built and fitted out.
- 05Testing and handoverEach system tested, then the building as a whole, with manuals, as-built drawings and training for the facility team.
FedEx’s first sort facility in Dubai, with every building service and its own cooling plant delivered by one contractor.
- One contract, and one party responsible, for every building service
- The district cooling plant and ETS room delivered inside the building contract