132/11 kV substations, section B
132 kV trough installation and cable laying.

- Client
- DEWA
- Consultant
- Khatib & Alami
- Main contractor
- Ghantoot Transport & General Contracting
- AZEMCO role
- Cable contractor
- Services
- Networks and substations, Utility networks
- Location
- Dubai
- Status
- Completed
- Contract value
- AED 4M

Built, tested and handed over.
AZEMCO was the cable contractor on 132/11 kV substations, section B for DEWA, with Khatib & Alami as consultant and Ghantoot Transport & General Contracting as main contractor. 132 kV trough installation and cable laying. The work covered networks and substations and utility networks.
More in power and renewable energy.

Solar PV portfolio
- Client
- DEWA, Etihad Energy Services and private owners
- Value
- AED 16.2M
Design, build and O&M of rooftop and carport solar PV plants: 6,349 kWp in all, from a 158 kWp mosque roof to a 2.8 MWp plant in Al Quoz.
- Solar PV and energy efficiency
- Operation and maintenance

Jebel Ali and Al Awir power stations
- Client
- DEWA / Etihad Energy Services
- Consultant
- Etihad ESCO
- Main contractor
- Philips
- Value
- AED 7M
Lighting refurbishment at two power stations.
- Electrical systems
- Solar PV and energy efficiency

11 kV works, Palm Jumeirah
- Client
- Nakheel
- Consultant
- Parsons
- Main contractor
- Power Advantage
- Value
- AED 3.5M
11 kV cables, transformers and earthing.
- Networks and substations