Etihad Rail Stage 2, Package 2D

GRP drainage pipeline, lighting and civil works for Etihad Rail’s Stage 2, Package 2D, delivered as one package for the main contractor, CRCC NPC JV.

Delivered forChina Railway Construction
Client
Etihad Rail
Main contractor
CRCC NPC JV
Consultant
Jacobs
Location
UAE
Our role
Package contractor
Contract value
AED 7M
Status
Completed
Etihad Rail Stage 2, Package 2D
AED 7Mcontract value
3services in one contract
Handed overand in operation
The brief

Three trades in one rail package.

On Etihad Rail’s Stage 2, Package 2D, AZEMCO laid the GRP pipeline, installed the lighting and carried out the civil works that go with them, for the main contractor, CRCC NPC JV, with Jacobs as consultant.

What the client needed
  • GRP pipeline, lighting and civil works delivered as one package
  • Work fitted into a corridor shared with other contractors
  • Live roads and existing services protected throughout
The challenges

What made it hard.

  1. 01

    Many contractors, one corridor

    Track, structures, systems and utilities contractors worked along the same corridor, so access and working areas had to be agreed every week.

  2. 02

    Live roads and existing services

    The works ran next to live roads and existing services, where a damaged cable or pipe would stop far more than our own work.

  3. 03

    Three trades, one sequence

    Drainage, lighting and civil works depend on each other: the pipe trench, the lighting bases and the cable ducts had to follow one sequence.

How we solved them

What we did about each one.

  1. Challenge 01Many contractors, one corridor
    Our response

    Access planned with the main contractor

    We planned our work fronts in the main contractor’s weekly coordination and kept to the areas we were given.

  2. Challenge 02Live roads and existing services
    Our response

    Services found before digging

    Every excavation started from the utility drawings, permits and trial pits, so existing services were located before machines went in.

  3. Challenge 03Three trades, one sequence
    Our response

    One crew plan for three trades

    We sequenced the GRP pipe laying, the civil works and the lighting as one plan, so each crew left the ground ready for the next.

How the work ran

From the first drawing to handover.

  1. 01Permits and surveyUtility permits and drawings obtained, and services located by trial pits.
  2. 02ExcavationTrenches and foundations opened in sequence along the corridor.
  3. 03GRP pipelinePipes laid, jointed and tested, with manholes and backfill.
  4. 04LightingBases, columns, cabling and fittings installed and tested.
  5. 05HandoverAreas reinstated and handed back to the main contractor.
The result

One package for Etihad Rail, followed by more: street lighting and civil works at Junction 3B, and the 132 kV and 11 kV diversions at E611 for DEWA and Etihad Rail.

What changed
  • Drainage, lighting and civil works delivered as one package
  • Further Etihad Rail work at Junction 3B and the E611 diversions