Skip to content
Industrial and logistics · Completed

Furnace and LEHR rebuild

MEP works for the rebuild of a glass furnace and LEHR.

Delivered forAl Tajir Glass
Furnace and LEHR rebuild
Client
Al Tajir Glass
Consultant
Spec
Main contractor
AZEMCO (main contractor)
AZEMCO role
MEP contractor
Location
Dubai
Status
Completed
Contract value
AED 8M
Furnace and LEHR rebuild
Photograph
Glass plant rebuild · services site planGLASS PLANT REBUILD · SERVICES SITE PLANFurnace hallLoading docksLV roomFire pumpsSubstation11 kVFire tankOfficesHydrant ring
Engineering drawing · illustrative
AED 8Mcontract value
2services in one contract
Handed overand in operation
What we did

Built, tested and handed over.

AZEMCO was the main contractor on Furnace and LEHR rebuild for Al Tajir Glass, with Spec as consultant. MEP works for the rebuild of a glass furnace and LEHR. The work covered electrical systems and hvac and district cooling.

Related projects

More in industrial and logistics.

Start a project

Planning a similar project?

Tell us the scope and the programme. We reply with the approvals involved, a programme and a priced proposal.